Expansions and Renovation of 770

This article traces the expansion and renovation of the central synagogue and beis midrash of 770 - Chabad World Headquarters, located on the lower floor (the basement).

Construction and expansion of 770, in 5752 (1991–92) (?)

The space was once a parking area for the ambulances of the local hospital. Over the years it became the largest and central synagogue of Chabad Chassidus and the site of the Rebbe's prayers and farbrengens. The synagogue is called the Zal HaGadol ("the large zal"), as distinct from the "Zal HaKatan" ("the small zal") on the entrance floor.

The Shalash edit

 
The Rebbe at prayer in the "Shalash"
 
The Rebbe praying in his place in the "Shalash"

To the left of the 770 building was a parking area for the ambulances of the private hospital that once operated there. After 770 was purchased by Agudas Chassidei Chabad, the courtyard was used for children's rallies and for the parade.

The courtyard was called the Shalash (Russian for a temporary structure).

Around 5714 (1953–54), as the crowds at the Rebbe's prayers and farbrengens grew too large for the "Zal HaKatan," the larger "Shalash" began to be used for farbrengens and for the prayers of the month of Tishrei. The large farbrengens during the winter, on Yud-Tes Kislev, Yud Shevat and Purim, were held in other, larger halls in the Crown Heights area.

First Expansion edit

As the Chabad community grew, more space was needed and the Shalash was used more and more. It was poorly maintained, which at times made it unbearable[1]. At the end of 5719 (1959) work began on the Shalash: it was sealed against rain, wind and cold, enclosed on its northern and southern sides (facing Eastern Parkway and Union Street), and roofed with a tarpaulin (replaced with schach on Sukkos). The renovation was completed in time for Rosh Hashanah 5721 (1960). The Rebbe's place of prayer was set in the southeastern corner. R' Zalman Blesofsky built a special platform for the Rebbe for farbrengens. It was collapsible, freeing the space when there was no farbrengen. Behind it was a window onto Union Street, where yeshivah students would stand to see the Rebbe; after a short time the Rebbe had the window closed.

Further renovations at that time made the place more comfortable: Rebbetzin Chaya Mushka Schneerson donated five chandeliers which were hung in the center of the Shalash. Ventilation windows were opened in the roof, which helped at ordinary times (though during farbrengens and crowded periods it was very hot). R' Yaakov Lipsker built a special platform for the Torah reading, made of strong wood and without many parts. Until then the Torah reading platforms broke every Simchas Torah under the pressure of the crowds; the new platform, ready in time for Simchas Torah, lasted thirty years. In 5749 (1988–89) it was replaced with a new one. After the renovation, the large farbrengens in outside halls ended and all events were held in 770.

Second Expansion edit

 
The synagogue hall after the second expansion

In the winter of 5725 (1964–65), the buildings on either side of 770 – 784 and 788 Eastern Parkway – were purchased. The purchase was made by R' Aharon Klein, who also helped finance it. The rest of the money came from the Rebbe himself, who did not want additional partners and owners in 770.

The initiative came from Mr. Aharon Klein, who proposed at yechidus to expand 770 all the way to Kingston Avenue. The Rebbe asked: "Are you sure we will need such a large synagogue?!" R' Aharon answered the Rebbe with confidence: "They will need an even larger one than that," and the Rebbe agreed.

The buildings were registered in R' Aharon's own name rather than that of the Vaad HaBinyan, which actually handled the expansion. Various explanations have been suggested, among them the bank's refusal to lend so large a sum to a synagogue without adequate guarantees. R' Aharon, who managed other large organizations in America (for example, Kollel Chabad), was apparently better known to the banks. Another suggestion is that the Rebbe instructed it, not wanting the code violations that occur in almost every construction project to be registered in Chabad's name. Upon completion of the expansion, ownership was transferred to Merkos L'Inyonei Chinuch. Some say the reason for registering the building in R' Aharon's name was that the previous owner of the building had asked his children not to sell the building to Lubavitch; therefore R' Aharon, who was not a Lubavitcher Chassid, bought it[2].

 
Chassidim at a farbrengen with the Rebbe in the Zal HaGadol passing a chair over their heads, after the second expansion

After the tenants were moved out, the first floor of 784, to the left of 770, was leveled, while yeshivah students and several Anash families were temporarily housed in 788, on the right.

In Elul 5727 (1967), work began on preparing the basement of building 784 to serve as a synagogue. The plan, which seemed unrealistic, was to finish within a month so that the Rosh Hashanah 5728 (1967) prayers could be held there. The expansion included: Stage 1 - excavating from the first floor down to the bottom of the basement, in order to create a space with a high ceiling. Stage 2 - breaking through the walls separating the 770 building from building 784, and Stage 3 - preparing the combined basement as a large prayer hall. The first stage progressed quickly, and it seemed that the construction would indeed be finished by Rosh Hashanah. Approaching the second stage, the workers discovered that the wall separating the buildings was made of reinforced concrete and iron and was three feet thick. It was twenty meters long, and it was impossible to finish this by Rosh Hashanah.

On the night of Erev Sukkos 5728 (1967), after the large wall had already been broken through, the workers discovered that there was another wall serving as the western foundation of building 784, and that breaking it was only possible with an engineer's approval. The workers broke a small part of it, and it was agreed to continue breaking it in the presence of an engineer.

The Chassidim and Temimim who were present kept up with the progress of the construction and understood that the renovation could not be stopped in the middle (since the next day was Erev Yom Tov and no work is done on Chol HaMoed); it turned out that the renovations would not be finished until after Simchas Torah. In a hasty decision, the bochurim took a long, heavy pipe that was intended for the building's heating pipes and began striking the wall with it. The bochurim worked energetically all night, during which several bochurim were lightly injured, and toward dawn the work was completed and the entire basement became one hall. Building 784 was left without engineering support. The Aron Kodesh and the Rebbe's platform were moved to the front of the basement.

The next day, they laid a ramp bridging the floors of the Shalash and 784, and cleaned the place of construction debris. The Chabad Chassidim waited for the Rebbe's entry into the "new synagogue." Before Mincha on Erev Sukkos, the Rebbe came down from his holy room and entered the Zal HaGadol. The Rebbe advanced quickly toward his new, more distant place, looking to the sides the whole time, with great joy visible on his face.

On the first day of Sukkos, thick iron beams were erected to temporarily support the building.

After the holiday, R' Yaakov Lipsker built forty new wooden benches, which he donated to 770. After the construction was completed, he decided to donate a new Aron Kodesh as well. He understood that the Rebbe wanted the Aron Kodesh not to be built into the wall, but outside of it. R' Yaakov brought a worker who built the wooden frame of the Aron, and R' Yaakov made the rest of the parts by hand with the help of his son.

Third Expansion edit

 
The "Zal HaGadol" during a farbrengen with the Rebbe after the third expansion, photographed from the window of the Broadcast Room
 
The "Zal HaGadol" on a Friday afternoon, almost empty of worshippers

Over the years the Chabad community grew, and already in 5728 (1967–68) the space was not enough to accommodate everyone. This time it was planned to expand the synagogue beneath the basement of building number 788. This time too, R' Aharon handled the construction, and he even received encouragement for it from the Rebbe[3]. In practice, the expansion work was delayed for five years, possibly due to a lack of financial means.

At the end of 5733 (1973), they began expanding the "Zal HaGadol," and this time too they planned for the synagogue to be ready by Rosh Hashanah. This time, no professional contractor was hired to manage the work; rather, the gabbaim themselves managed it. R' Zalman Lipsker was appointed on behalf of the Vaad HaBinyan to personally supervise the construction work. The foreman on site was a strong man who could function with only one hand; nevertheless, the work progressed at a rapid pace. The gabbaim made a significant contribution to speeding up the work, as several of them would complete the workers' work of that day every night. The most prominent among them were R' Zalman Blesofsky together with his son R' Yehuda Blesofsky, R' Zalman Lipsker and his brother R' Yosef Yitzchak Lipsker. R' Aharon was less involved in this construction than in the previous one.

During the expansion, they had to excavate in the place of the stores that opened onto Kingston Avenue at street level. Temporary pillars were erected to support the building, and toward the end of construction they wanted to remove them so they would not interfere with the spread of the chazzan's voice. The removal of the pillars was supervised by an engineer who gave instructions. One of the members of the "Vaad HaBinyan," who was concerned about removing the pillars, went to consult another engineer. The latter answered him that "in everything there is danger." That committee member entered the Rebbe and related the engineer's answer. The Rebbe's answer was that if there is danger in it, they should not remove the pillars. A short time later, in the middle of the construction process, one of the small tractors working inside the 770 area collided with one of the pillars, and the pillar was knocked out of place, raising fears that the building would collapse. After a few minutes, when nothing happened, it was proven that there was no problem, and the pillars were removed.

Special, expensive bricks were donated for the "eastern" wall of the synagogue. Over the years, since most of the photographs of the Rebbe taken in 770 were against the background of this wall, it became one of the identifying marks of 770. At the top of this wall there is an outward slope, so that the voice of the chazzan will be "thrown" back toward the worshippers.

On the night of Erev Rosh Hashanah 5734 (1973), almost the entire building was ready, except for the bricks of the eastern wall, which needed coating and finishing. That night several gabbaim worked to finish the construction until daybreak, at which point the "Zal HaGadol" was expanded to its maximum capacity. The floor was crooked and all of 770 stood on a slope (for several years, until it was leveled), the panels had not yet been attached, and the women's section on the Eastern Parkway side was only a concrete surface - but the construction as a whole was completed. After the holidays the work resumed and the workers dealt with finishing the building. R' Zalman Lipsker pasted new wallpaper on the walls in order to make their color uniform throughout the building. Several Chassidim finished renovating the women's section, and also built stairs from the women's section to the second floor.

This expansion did not include the area beneath the women's section on the Eastern Parkway side. Several years later, a room for coats and storage lockers was made at the eastern end, which later became a sort of "second room," until the stage at which the restrooms downstairs were renovated, the electrical room that was there was cleared out, and the entire area beneath the women's section was opened up; beneath it a room was built called "Lishkas Osei Chavitin / Vaad Seudas Shlomo," in which everything needed for food for the farbrengens in 770, "mezonos" before prayers, and more, is prepared.

Laying of the Cornerstone edit

 
The Rebbe lays the cornerstone for the latest expansion of 770 (Elul 5748 (1988))

Over the years, the Chabad community grew and developed to great proportions. During the holidays, especially in the month of Tishrei, 770 became a bustling place and a pilgrimage center for thousands of people from all over the world. The place became too small to hold the ever-growing crowd. For a long time there was talk of plans to expand the "Zal HaGadol" (main study hall), and a modest "cornerstone laying" ceremony was planned in preparation for the expansion. On 17 Elul 5748 (1988), the Rebbe prayed as usual at his home on President Street. After the Mincha prayer, a dollar distribution took place, during which the chairman of the "Keren Yedidei Machaneh Yisroel" fund, the philanthropist Mr. David Chase, approached and told the Rebbe that he planned to expand and enlarge the 770 building into a large and magnificent building. He explained all the details of the matter to the Rebbe, and then requested and invited the Rebbe to participate in the cornerstone laying ceremony that he wished to hold that same day in the courtyard of 770. Surprisingly, the Rebbe accepted the invitation and made his participation conditional on Mr. Chase speaking during the ceremony in Yiddish, which was his mother tongue. Mr. Chase agreed to the condition and said to the Rebbe in Yiddish: "See you at 5:00."

The Rebbe's sudden agreement to participate in the ceremony caused the organizers to speed up the preparations. Within minutes, the ground in front of 770 was prepared and a special platform was erected for the Rebbe, on which a lectern and a microphone were placed. A large crowd began streaming to the site of the event, positioning themselves on improvised bleachers ("pyramids") set up on the street. A sign was hung on the front of the building: "Great shall be the glory of this House; for a good and sweet year." At exactly 5:00 the Rebbe arrived in his car. The Rebbe got out of the car, turned toward the improvised platform, and delivered a sichah for about ten minutes. In the sichah, the Rebbe spoke about the meaning of the name given to events of this kind in "the language of the country" - "groundbreaking," the breaking of the ground - as well as about the spiritual significance of laying a cornerstone, comparing it to the Foundation Stone from which the entire world was founded, and whose location was specifically in the Holy of Holies. At the conclusion of the sichah, Mr. Chase was honored to speak in Yiddish, as had been agreed.

Mr. Chase opened his remarks by speaking of the great privilege that had fallen to his lot to build here the Rebbe's study hall and world center. He related with emotion how during the Holocaust he had seen the Germans destroy all the synagogues in his town, and had not believed that the day would come when he himself would build a synagogue. Mr. Chase added: "Rebbe, I did commit to you to speak in Yiddish, but what can I do, I have almost completely forgotten this language and it is difficult for me. Rebbe, ich hob dir lieb zeier zeier a sach (Rebbe, I love you very, very much)." Upon hearing the conclusion of Chase's speech in Yiddish, the Rebbe smiled a broad smile with a radiant face.

 
The Rebbe smiles at Mr. Chase

Afterwards, the Rebbe asked that the Rashag also say words of blessing. The Rashag mentioned that in these days, marking 91 years since the founding of Tomchei Temimim, it was a special privilege at that time to expand the house of our Rebbeim, which also serves as the building of the Central Tomchei Temimim Yeshiva. Finally, he blessed the Rebbe with tremendous success and with nachas from all the Chassidim.

After the Rashag's speech, the Rebbe descended from the platform and approached the pit that had been dug for the cornerstone. The Rebbe took a shovel in his hand and pushed the sand aside, bent down, lifted with his hands the stone that had been placed nearby, and set it in the pit. He again took the shovel in his hands and covered the stone with a little sand. Afterwards, the philanthropist Mr. Chase, members of the secretariat, and the distinguished rabbis were honored with filling the pit using the shovel. After laying the cornerstone, the Rebbe walked toward the opening of the fence that enclosed the area, stopped, and said that he wished to distribute dollars. The lectern was immediately brought down from the platform and the Rebbe began the distribution[4]. At first there was great commotion, since no one had ever thought about how to create a line for receiving a dollar in the area in front of the building, but order was soon established and the crowd began to sing in the background, accompanied by the band. The distribution lasted about an hour and a quarter, and afterwards, to the sound of the singing of "Samei'ach Tesamach" and with the Rebbe waving his hand, the Rebbe drove back to his home.

The Plans Approved by the Rebbe edit

At the time of the cornerstone laying, the architect Yehuda Prag prepared plans for the expansion of 770, and the Rebbe approved the plans.

For many years the details of the plans were not known to the general public, and following the public stir regarding the expansion, in Shevat 5784 (2024) the architect Yehuda Prag agreed to reveal the plans, first in a lecture (Hebrew) at the Yeshivas HaMelech HaMoshiach, and shortly afterwards in an extensive interview in the Beis Moshiach weekly[5]:

Eventually, the committee members told Mr. Yehuda that the Rebbe had rejected the limited plans they had sought to carry out, and that he specifically wanted Mr. Yehuda's plans. That same day he passed by at the dollar distribution, and the gabbai, Rabbi Zev Katz, introduced him to the Rebbe as the architect of the plans and added that he was planning to return to Jerusalem. The Rebbe gave Yehuda one dollar for tzedakah to give in Jerusalem, and the Rebbe gave him another dollar "for the success of the building that you are planning for us" (in Yiddish). After he moved on, the Rebbe called him back and said to him in Yiddish: "Carry out all the blessings, and don't disappoint me."

In practice, the expansion that took place in those years was only partial - the restrooms were moved down to a lower level, as were adjacent halls that were built - but in 5754 (1993–94) the momentum of construction came to a complete halt.

In 5764 (2003–04), Yehuda Prag was again called to New York by the Dreizin and Branover families, who sought to advance the project. They even asked him to design a more expanded version. But Yehuda told them that he had instructions and directives from the Rebbe, and that he must construct the building as the Rebbe had requested. Originally, the area of the building is one thousand nine hundred meters, and in the construction plan that Mr. Yehuda presented to the Rebbe and that was approved by him, there are seven thousand seven hundred meters. In the new plan that they asked Yehuda to design, the place could hold almost double the area that the Rebbe had approved to build. But then Yehuda received a phone call in which he was told: "Yehuda, hold off on the plans and on continuing the work; disputes have arisen, and until the disputes are resolved, there is no point in moving forward."

In connection with the renewed awakening regarding the expansion of 770 in 5784 (2023–24), Yehuda related[6] further details about the appearance of the building plan: entrances to the building will be on Union and Eastern Parkway; after a short lobby, the entrance will continue into a large, high hall spanning from side to side, with the Rebbe's platform and the Aron Kodesh remaining in their place, and behind and above it a window. There will be a passage between the 770 building and the new building. An additional floor was planned as a gallery floor for men, another floor for the women's section, and a spacious basement for the kiddush hall. The new building will be built with advanced technology, without support columns in the center of the building. In addition, there will also be room for offices and a library on the sides of the study hall, which at peak times will open into one large space, allowing a large crowd of worshippers to be in the same place simultaneously.

The Balcony edit

 
The Rebbe encourages the singing of Yechi Adoneinu from the balcony

In 5753 (1992–93), due to the Rebbe's state of health, a number of changes were made in 770. Before Rosh Hashanah, a special prayer room was built for the Rebbe above the bleachers ("pyramids") on the western side of 770, with a direct connection to the Rebbe's room. In preparation for Simchas Torah, a balcony was also built, to enable the Rebbe's participation in the hakafos in a way that he could be seen well. After the holiday of Sukkos, a staircase was built from the balcony to the platform in 770. This was following the Rebbe's sudden descent into 770, and in order to make it possible should the Rebbe wish to come down again. During the period in which the Rebbe appeared on the balcony, the five chandeliers that hung from the ceiling of 770 were taken down, to enable the crowd to see the Rebbe.

In 5754 (1993–94), the structure of the balcony was changed slightly, in a way that would make it easier for the Rebbe to look down and see the Chassidim.

Further Renovations edit

 
A model of the expansion of 770 from 5753 (1992–93)

In 5752 (1991–92), a plan began for a significant renovation of the entrance to the main zal. The plan was with the assistance of the philanthropist R' Yosef Yitzchak Gutnick together with a worldwide fundraising campaign in which Chassidim of Chabad throughout the entire world participated. The work itself took several years, and was completed in 5755 (1994–95), when the entire entrance plaza of 770 was renovated. In addition, spacious restrooms were built on the basement floor beneath the main zal, replacing the restrooms that had been inside the main zal. The place where the previous restrooms had stood was adapted and annexed to the "main zal".

In 5755 (1994–95), the old ceiling - from which the air-conditioning ducts and electrical fixtures protruded - was replaced with an acoustic ceiling. The parquet flooring in the entire zal was also replaced. In Elul 5761 (2001), a new women's section was built facing Union Street, with about 50 additional seats for women[7]. In the winter of 5762 (2001–02), parts of the Aron Kodesh were repainted. At the beginning of 5765 (2004–05), new fans were installed, after the old ones had been removed with the renovation of the ceiling in 5755 (1994–95). In Cheshvan 5766 (2005), the floor of 770 was replaced with a new floor (after more than 11 years). In 5768 (2007–08), a chandelier was installed above the Torah-reading platform, similar to the chandeliers that had been in the hall until 5753 (1992–93).

In 5769 (2008–09), the small zal was renovated, during which an automatic screen descending from the ceiling by remote control was installed - used for daily video screenings by the committee of Letzayer Pnei HaRav. In the winter of 5773 (2012–13), another chandelier was added on the western side of 770, parallel to the previous chandelier. In Tishrei 5774 (2013), three more new chandeliers were added in front of the Aron Kodesh, one large one and two smaller ones on either side of it; these chandeliers give the Aron Kodesh a regal splendor. In 5776 (2015–16), the stairs at the entrance to the 770 building were replaced. In Tammuz 5778 (2018), the prayer platform was repaired and renovated, and in preparation for the month of Tishrei the farbrengen platform and the Torah reading platform were renovated, and the pillars and benches of 770 were painted[8]. In Menachem Av 5779 (2019), the floor of 770 was replaced according to the instruction of the gabbaim. In preparation for Tishrei 5780 (2019), the stairs leading from the first floor to the main zal were renovated[9].

 
The front of 770 in Elul 5782 (2022), after the renovation of the entrance to 770 and the addition of underfloor heating, together with a magnificent engraving of the number 770 by Bedek HaBayis (770)

In Elul 5782 (2022), the entrance to 770 was renovated with underfloor heating that provides comfort when entering the compound even in the snowy winter months, together with a magnificent engraving of the number 770[10]. In Shevat 5783 (2023), a door was opened connecting the main zal with the Kingston women's section. In Sivan 5783 (2023), the size of the women's section was doubled, and seats were added for the benefit of the bochurim who study there during the week, as well as places for women on Shabbos[11].

In the months of Adar 5784 (2024), the eastern wall of the main zal was repainted white.

At the end of the month of Adar and the beginning of the month of Nissan 5785 (2025), the acoustic ceiling was replaced, 30 years after its installation.

At the end of the month of Tishrei 5786 (2025), demolition began of the kollel building behind Beis Chayeinu – 770, which had stood desolate for two decades. In its place, with the help of Hashem, a spacious temporary tent will be erected on this site, to serve as a new and roomy zal for the bochurim who study in the beis midrash. The planned tent will hold 300 seats, and will provide a dignified, comfortable and accessible atmosphere for learning[12].

Expansion of the Main Zal 5787 edit

 
The construction work (Cheshvan 5787)

In 5782 (2022), the directors of the Kollel Avreichim announced the start of a project to demolish the old kollel building and erect a new building for the students of the Kvutza, with a spacious hall that would include about 300 seats and additional study rooms[13].

In practice, only at the end of the month of Tishrei 5786 (2025) did the demolition work begin on the old 'kollel' building located behind 770, which had stood desolate for about 25 years[14].

Toward the end of Tishrei 5787 (2026), construction work began on the site of the demolished building, and in place of the 'Shalash' that had not been joined to the synagogue in its first expansion, to erect a new and spacious beis midrash that would be connected to the zal building, holding more than 300 seats for the Temimim and Anash. The work was completed in the days close to the beginning of the International Kinus HaShluchim 5787[15][16].

Above the entrance door on the outside, the original sign "Ohel Yosef Yitzchak Lubavitch" was hung, which had been on the kollel building since the Seforim Case in 5745 (1985)[17].

During the construction, the corner in which the Rebbe prayed in the 'Shalash' was left exposed, where the original stone cladding can be seen[18].

Only prayers and Torah study will take place in the hall, and it will close every evening at 22:00[19].

Bedek HaBayis Fund edit

Bedek HaBayis is the name of an organization founded at the request of Rebbetzin Chaya Mushka in 5739 (1978–79). Its role is to see to the maintenance of the 770 building, that is, the original building purchased in 5700 (1939–40).

At that time, the library of the Frierdiker Rebbe was also under the fund's responsibility. R' Chaim Boruch Halberstam is in charge of the fund's management and activities. In the past, the fund was managed by Rabbi Avraham Lipskar and Rabbi Yitzchak Springer, assisted by Rabbi Chaim Sholom Dovber Lipskar.

One of the charity boxes designated for this cause is the large box in the entrance lobby. The Rebbe regularly gave tzedakah into it, and he would also instruct the children who received tzedakah coins from him as he went out to the prayers to put the coins into this box. Several times he even lifted one of the children in his arms after the child could not reach the box's slot.

The box was installed in 5722 (1961–62) for Keren Shneur, and after the fund ended its activity, its use was converted to "Bedek HaBayis".

Many times, those in charge of the box would empty it before the Rebbe passed by it, and afterwards they would sell the coins that the Rebbe had dropped into it.

Since 5763 (2002–03), Rabbi Boruch Shlomo Eliyahu Cunin has contributed toward the payment for the floor on which the Rebbe's room is located, funds part of the water and electricity bills, and sees to the renovation of Beis Chayeinu.

Further Reading edit

External Links edit

References edit

  1. ↑ A sichah of the Rebbe from 5718 (1957–58) is well known, concerning the Shalash, of which the gabbai R' Yochanan Gordon said: "Az s'iz kalt un shmutzik" ("that it is cold and dirty").
  2. ↑ So related R' Dovid Kratz, who was in 770 during those years.
  3. ↑ In a letter that R' Aharon wrote to the Rebbe on 22 Iyar 5728 (1968), in which he reported on the activity of his "Tefillin Truck" (the first version of the Mitzvah Tank), the Rebbe answered: "Many thanks for the good tidings; may he likewise finally report good news also regarding the expansion of the synagogue and its construction."
  4. ↑ The dollar distribution event (Hebrew) (photos) - Chabad Info
  5. ↑ Issue 1395
  6. ↑ In the Beis Moshiach weekly of 16 Shevat 5784 (2024).
  7. ↑ The women's section was built on the site of the stairs that led down from the balcony to the main zal
  8. ↑ The pillars are painted almost every year in preparation for the month of Nissan, and the benches in preparation for the month of Elul
  9. ↑ This is what the 770 stairwell looks like at the end of extensive renovation work
  10. ↑ Beis Chayeinu: completion of the renovations and engraving of the number on the front of 770 (Hebrew)
  11. ↑ For the bochurim: new places were built in the Kingston women's section (Hebrew)
  12. ↑ A temporary solution to the crowding in 770: a new zal for 300 bochurim (col.org.il) (Hebrew), Col.org.il
  13. ↑ Report, Anash.org.
  14. ↑ Avremke Eisenstein, "Exposé: The Abandoned Building Behind 770 Will Be Demolished for a Study Zal for Bochurim", Chabad.info (Hebrew), 30 Tishrei 5786.
  15. ↑ Documentation from the Site: The New Beis Midrash Behind 770 Nearing Completion, Chabad.info (Hebrew).
  16. ↑ Avremke Eisenstein, "Construction of the Beis Midrash in the Back Part of 770 Completed", Chabad.info (Hebrew), 25 Cheshvan 5787.
  17. ↑ "The Historic Sign Returns to Its Place", Col.org.il (Hebrew), 24 Cheshvan 5787 (04.11.2026).
  18. ↑ "This Is How the Rebbe's Place of Prayer Looks Today", Col.org.il (Hebrew), 28 Cheshvan 5787 (08.11.2026).
  19. ↑ Avremke Eisenstein, "Expansion of 770: Alongside the Enthusiasm, It Appears There Will Be a Limited Format", Chabad.info (Hebrew), 22 Cheshvan 5787.